Efficiency Comparison and Man-Day Calculation in Work Completion

Efficiency Comparison and Man-Day Calculation in Work Completion

Understanding the efficiency of different groups in completing a piece of work can be crucial for project management and resource allocation. This article delves into various examples of calculating the time required for a given number of men and women to finish a task, and how to convert these into man-days, a unit used to express the amount of work done.

Introduction

This article will explore the concept of work efficiency among men and women, and how to calculate the time required to complete a project using different group compositions. The key concepts include the conversion of work done by men and women into a common unit, known as man-days, and the application of this unit to find the time required to complete a specific piece of work.

Example 1: 4 Men and 5 Women vs. 12 Men and 15 Women

The problem states that 12 men and 15 women can finish a task in 20 days. To solve for 4 men and 5 women, we will calculate the work done per day by both men and women, and then find the total time required by the smaller group.

Work Rate Calculation

Firstly, let's calculate the work rates for men and women:

12 men complete the work in 20 days, so the work rate for 12 men is 1/20. The work rate for 1 man is therefore 1/144 (1/20 ÷ 12). The work rate for 12 men in 1 day is 12/144 1/12. Similarly, the work rate for 1 woman is 1/280 (1/20 ÷ 15), and for 15 women, it is 15/280 3/56. Therefore, the combined work rate for 4 men and 5 women is 4/144 5/280 7/56 6/56 13/56.

Time Calculation

The total time required for 4 men and 5 women to complete the work is calculated as follows:

Time required 56/13 ≈ 4.31 days, or 4 days and 4/13 days.

Example 2: Man-Days and Work Efficiency

In another scenario, 3 men can complete a task in 20 days, and 6 women in the same period. We need to find the time required for 15 men and 24 women to complete the task.

Work Rate and Man-Days

First, calculate the individual work rates:

1 man completes the work in 60 days, so the work rate is 1/60. 1 woman completes the work in 120 days, so the work rate is 1/120.

Next, determine the work rates for the combined group:

15 men in 1 day 15/60 1/4 of the work. 24 women in 1 day 24/120 1/5 of the work. Combined work rate 1/4 1/5 5/20 4/20 9/20 of the work per day.

The time required is the reciprocal of the combined work rate:

Time required 20/9 ≈ 2.22 days, or 2 days and 3 hours (20 minutes).

Example 3: Man-Days and Man-Woman Equivalence

A different approach involves converting man-woman equivalents into days. Let's consider another example where 5 men and 18 mandays and 6 women and 18 wodays are given.

Man-Days and Equivalence

A common unit for work performed by a group is to use man-days, which represents the effort of one man working for one day. Here, mandays and wodays (woman days) are used to represent the effort in terms of men and women, respectively.

The combined effort of 5 men and 18 mandays, and 6 women and 18 wodays can be expressed in terms of man-days:

5 men 5 man-days. 18 mandays 18 man-days. 6 women 6 woman-days. 18 wodays 18 woman-days. Total effort in man-days 5 18 6 18 47 man-days.

The number of days required can be calculated as the total effort divided by the daily effort provided by 15 men and 24 women:

Days required 47/18 ≈ 2.61 days, or 2 days and 14.67 hours.

Conclusion

Understanding work efficiency and converting work among men and women into man-days can be invaluable for project managers and resource planners. By using these techniques, one can optimize resource allocation and ensure tasks are completed on time.

Key takeaways:

Work done can be expressed in man-days for easier comparison and calculation. The efficiency of a group can be determined by individual work rates and combined rates. Conversion between man-days, mandays, and wodays provides a standardized approach to resource allocation.